Metro Centre

Metro Centre

Contracted by SAS Energy, we delivered support for a 1000kW carport system. This involved digging foundations with our own Bobcat wheel saw before installing rebar cafes holding 7m3 of X40 concrete to form the foundations.  We then fitted large bluetop uprights with...
Gateshead Civic Centre

Gateshead Civic Centre

Mechanical, electrical & civil installation of Bluetop Carport System, consisting of: 360 x TRINA VERTEX TSM-DE09.08 (400W) 2 Bay carport system with 2 no. solaredge inverters. This project was a very intense project with out-of-hours digging and tarmac...
DPD Leicester

DPD Leicester

Our second job consisted of a mechanical installation, including of all containment on the roof space, covering 2,218.4m2 of the...